Psaros / Projects / Under Construction

Current estimated completion date - Mid 2018

See the progress here.

East Bank December 2017

Ground Floor:    Window Frames Installed

                             Block work completed

                             Canopy steel completed

Mez Floor:          Underslung hydraulics and electrical progressing

First Floor:          Cabinets installed

                             First coat paint completed

                             Tiles commenced

Second Floor:    First coat paint commenced

                             Screed completed

                             Cabinets commenced

Third Floor:        Sheeting commenced

                             Screed completed

 Fourth Floor:    Pronto and frame work completed

                             Window frames installed

                             Screed completed  

Fifth Floor:         Pronto panel and blue board completed

                             Window frames installed                               

                             Screed completed

Sixth Floor:         Framing completed

Seventh Floor:   Pronto walls commenced

                             Canopy steel complete

                             Roof cover completed

East Bank Nov 17

Ground Floor:    Window Frames Installed

                             Block work completed

Mez Floor:          Underslung hydraulics and electrical progressing

First Floor:          Cabinets installed

                              First coat paint completed 

Second Floor:     First coat paint commenced

                              Screed completed

Third Floor:         Sheeting commenced

                              Screed completed

Fourth Floor:      Pronto and frame work completed

                              Window frames installed

                              Screed completed

Fifth Floor:          Pronto panel and blue board completed

                              Top and bottom track completed

 Sixth Floor:         Formwork stripped

                              Pronto set out

Seventh Floor:    Precast Walls completed

                              Roof cover commenced

                              Structural steel commenced

East Bank Sep 2017

Ground Floor:   Pronto walls commenced to ground floor units and tenancies.

                            Mech ducting instillations underway

                            Hydraulic instillations underway

                            Electrical instillations underway

 Mez Floor:        Brickwork to stores underway

                            Hydraulic and electrical instillations underway  

 First Floor:        Pronto panels 90% completed

                             Frame work underway

                             Hydraulic stack work underway

                             Electrical cabling underway

                             WPM to balconies underway

Second Floor:    Pronto panels commenced

 Third Floor:       Slab Completed, strip to commence week commencing 9/10/17

 Fourth Floor:     Ausdeck completed

                             Steel completed to pour 1 – Concrete 2/10/17

                             Steel to pour 2 underway

East Bank August 2017

Ground Floor:   

Slab on ground complete

Western Power removed LV service

Transformer and LV frame installed – Waiting to confirm cable instillation date.

Mez Floor:        

Formwork stripping progressing

First Floor:        

Slab completed

Panels and columns completed

Second Floor:  

Pour 1 Ausdeck installed

Steel fixing commenced 

East Bank July 2017

Monthly update at Eastbank for July.

Ground Floor:   

Ground slabs completed up to area 4

Temp lighting and temp accommodation installed to ground floor carpark

Mez Floor:         

Slab completed

Precast walls and columns completed

Formwork to insitu sections underway – Pour booked for Thursday 3/8/17

First Floor:          

Pour 1 Ausdeck installed

Steel fixing progressing – Pour booked for Wednesday 2/8/17

August Targets,

Complete ground works and first floor, progress to the first floor structure

East Bank June 2017

Monthly update at Eastbank for June.

 

Ground Floor:

  • Tower crane installed
  • Ground works progressing – Residential footings to commence 3/7/17
  • Carpark slab and commercial tenancies poured
  • Pre-Cast - 3 x Core’s walls stood
  • Columns to commercial and carpark slabs
  • Perimeter walls stood to bottom of ramp
  • Mez Floor panels commenced

 

July Targets:

  • Complete ground works and Mez slab, progress to the first floor structure

East Bank May 2017

Works commenced 8/5/17.

Bulk earthworks completed, detailed excavations to footings underway.

Footings poured to crane, stair 2, SF1+2 and commercial 3.

Slab poured to commercial 3.

Piles to East and Southern elevations completed.

Deep sewer pipe work and mains connection completed

Tower crane install to go ahead 1/6/17

 

Works to progress out of the ground over the next month with column and panel instillations to commence as the slabs go down. 