Psaros / Projects / Under Construction

Current estimated completion date - First quarter 2018

See the progress here.

Sundance August 2017

Basement

Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

Tiling complete

Final paint 95% complete

Level 01:

Unit 09 - 27

Stone tops 95% complete

Level 02:

Unit 28 - 46

Kitchens 10% complete

Level 03:

Unit 47 - 57

Sheeting flushing complete

 Level 04:

Unit 58 - 68

Sheeting 50% complete

Level 05:

Unit 69 - 79

Framing 50% complete

Level 06:

Unit 80 - 90

Services 50% complete

Level 07:

Unit 91 - 100

Structural steel 50% complete

Sundance May 2017

During the last 4 weeks we have completed the below

Basement:

  • Storerooms 45% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 06  

Level 01:

Unit 09 - 27

  • Level 01 formwork 100% stripped out
  • Level 01 Underslung plumbing 50% complete

Level 02:

Unit 28 - 46

  • Level 02 concrete poured 100% installed
  • Level 02 wall panels 80% installed

Level 03:

Unit 47 - 57

  • Level 03 Floor panels 50% installed

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor internal wall framing Unit 01 – 08  
  • Ground floor internal wiring and plumbing 100% complete

Level 01:

Unit 09 - 27

  • Ground floor internal wall framing

Level 02:

Unit 28 - 46

  • Level 02 formwork 100% stripped out
  • Level 02 underslung plumbing

Level 03:

Unit 47 - 57

  • Level 03 concrete poured 100% complete 

Sundance April 2017

During the last 4 weeks we have completed the below;

Basement:

  • 100% Formwork stripped out

Ground Floor:  

Unit 01 – 08

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured
  • 50% Formwork stripped out

Level 01:

Unit 09 - 27

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 50% installed
  • Level 01 50% Concrete poured

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 50% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 05  

Level 01:

Unit 09 - 27

  • Level 01 formwork 50% stripped out

Level 02:

Unit 28 - 46

  • Level 02 floor panels 100% installed
  • Level 02 wall panels 50% installed

Level 02 concrete poured 50% installed

Sundance March 2017

During the last 4 weeks we have been working on the below;

Basement

  • 100% Footings complete
  • Basement ground slab 100% complete
  • Basement precast walls and columns 100 % complete
  • 50% Basement formwork stripped out

Ground Floor

  • Ground floor precast floor panels 100% installed
  • Ground floor slab 75% Concrete poured

Level 01

  • Floor panels started

Over the next 4 weeks we will be working on completing the below;

Basement

  • 100% Formwork stripped out
  • Basement storerooms 20% Complete

Ground Floor

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured

Level 01

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 20% installed
  • Level 01 25% Concrete poured 

Sundance February 2017

During the last 4 weeks we will be have been working on the below:

Basement

  • 90% Footings complete
  • Basement ground slab 75% complete
  • Basement precast walls and columns 80 % complete

Ground Floor

  • Ground floor precast panels 50% complete

 

 

Sundance January 2017

During the last 4 weeks we will be have been working on the below:

Basement

  • 50% Footings complete
  • Crane base and Crane installation complete
  • Bulk excavation 90% complete
  • Precast concrete stairwell and lift shaft wall installation complete
  • Plumbing and electrical ground works 75% complete

Over the next 4 weeks we will be working on completing the below

Basement

100% Footings complete

  • Basement ground slab 75% complete
  • Basement precast walls and columns 50 % complete

Sundance December 2016

During December we have been working on:

Basement

  • Sheet piling 100% complete
  • Bulk Excavation 70% complete
  • Soakwell install 50% complete
  • Footing excavation 30% complete
  • Crane base and feet install 100% complete

:

Sundance November 2016

During the last 4 weeks we will be have been working on the below:

Basement

  • Sheet piling
  • Grout injection
  • Bulk excavation

Over the next 4 weeks we will be working on completing the below

Basement

  • 20% Footings
  • Crane base installation
  • Bulk excavation