Psaros / Projects / Under Construction

Projects under construction

Want to see how construction is progressing?

Please click on the project you would like to see a construction update for. Visit our Current Projects to see the superb opportunities still available at the sites under construction.

Sundance by Psaros

Current estimated completion date - First quarter 2018

See the progress here.

East Bank by Psaros

Current estimated completion date - Mid 2018

See the progress here.

Current estimated completion date - First quarter 2018

See the progress here.

Sundance Sep 17

  • Basement  cleaning all storerooms.
  • Ground floor - all complete other than front balcony’s.
  • First floor – timber flooring 80%   carpets start Monday.
  • Second floor- levelling concrete floors ready for timber flooring.
  • Third floor –breezeway tiling complete internal tiling 70%.
  • Fourth floor- tiling breezeway today     internal tiling next week.
  • Fifth floor –kitchen install  60% waterproofing breezeway  Monday.
  • Sixth floor –fully framed 40% gyprocked scaffold strip Wednesday.  
  • Seventh floor –framing in progress –breezeway soffits in progress –roof cover complete Wednesday –screeding internally in progress.
  • Pool deck structural steel started, screeding planters started and torch on started.

Sundance August 2017

Basement

Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

Tiling complete

Final paint 95% complete

Level 01:

Unit 09 - 27

Stone tops 95% complete

Level 02:

Unit 28 - 46

Kitchens 10% complete

Level 03:

Unit 47 - 57

Sheeting flushing complete

 Level 04:

Unit 58 - 68

Sheeting 50% complete

Level 05:

Unit 69 - 79

Framing 50% complete

Level 06:

Unit 80 - 90

Services 50% complete

Level 07:

Unit 91 - 100

Structural steel 50% complete

Sundance May 2017

During the last 4 weeks we have completed the below

Basement:

  • Storerooms 45% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 06  

Level 01:

Unit 09 - 27

  • Level 01 formwork 100% stripped out
  • Level 01 Underslung plumbing 50% complete

Level 02:

Unit 28 - 46

  • Level 02 concrete poured 100% installed
  • Level 02 wall panels 80% installed

Level 03:

Unit 47 - 57

  • Level 03 Floor panels 50% installed

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor internal wall framing Unit 01 – 08  
  • Ground floor internal wiring and plumbing 100% complete

Level 01:

Unit 09 - 27

  • Ground floor internal wall framing

Level 02:

Unit 28 - 46

  • Level 02 formwork 100% stripped out
  • Level 02 underslung plumbing

Level 03:

Unit 47 - 57

  • Level 03 concrete poured 100% complete 

Sundance April 2017

During the last 4 weeks we have completed the below;

Basement:

  • 100% Formwork stripped out

Ground Floor:  

Unit 01 – 08

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured
  • 50% Formwork stripped out

Level 01:

Unit 09 - 27

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 50% installed
  • Level 01 50% Concrete poured

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 50% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 05  

Level 01:

Unit 09 - 27

  • Level 01 formwork 50% stripped out

Level 02:

Unit 28 - 46

  • Level 02 floor panels 100% installed
  • Level 02 wall panels 50% installed

Level 02 concrete poured 50% installed

Sundance March 2017

During the last 4 weeks we have been working on the below;

Basement

  • 100% Footings complete
  • Basement ground slab 100% complete
  • Basement precast walls and columns 100 % complete
  • 50% Basement formwork stripped out

Ground Floor

  • Ground floor precast floor panels 100% installed
  • Ground floor slab 75% Concrete poured

Level 01

  • Floor panels started

Over the next 4 weeks we will be working on completing the below;

Basement

  • 100% Formwork stripped out
  • Basement storerooms 20% Complete

Ground Floor

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured

Level 01

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 20% installed
  • Level 01 25% Concrete poured 

Sundance February 2017

During the last 4 weeks we will be have been working on the below:

Basement

  • 90% Footings complete
  • Basement ground slab 75% complete
  • Basement precast walls and columns 80 % complete

Ground Floor

  • Ground floor precast panels 50% complete

 

 

Sundance January 2017

During the last 4 weeks we will be have been working on the below:

Basement

  • 50% Footings complete
  • Crane base and Crane installation complete
  • Bulk excavation 90% complete
  • Precast concrete stairwell and lift shaft wall installation complete
  • Plumbing and electrical ground works 75% complete

Over the next 4 weeks we will be working on completing the below

Basement

100% Footings complete

  • Basement ground slab 75% complete
  • Basement precast walls and columns 50 % complete

Sundance December 2016

During December we have been working on:

Basement

  • Sheet piling 100% complete
  • Bulk Excavation 70% complete
  • Soakwell install 50% complete
  • Footing excavation 30% complete
  • Crane base and feet install 100% complete

:

Sundance November 2016

During the last 4 weeks we will be have been working on the below:

Basement

  • Sheet piling
  • Grout injection
  • Bulk excavation

Over the next 4 weeks we will be working on completing the below

Basement

  • 20% Footings
  • Crane base installation
  • Bulk excavation

Current estimated completion date - Mid 2018

See the progress here.

East Bank Sep 2017

Ground Floor:   Pronto walls commenced to ground floor units and tenancies.

                            Mech ducting instillations underway

                            Hydraulic instillations underway

                            Electrical instillations underway

 Mez Floor:        Brickwork to stores underway

                            Hydraulic and electrical instillations underway  

 First Floor:        Pronto panels 90% completed

                             Frame work underway

                             Hydraulic stack work underway

                             Electrical cabling underway

                             WPM to balconies underway

Second Floor:    Pronto panels commenced

 Third Floor:       Slab Completed, strip to commence week commencing 9/10/17

 Fourth Floor:     Ausdeck completed

                             Steel completed to pour 1 – Concrete 2/10/17

                             Steel to pour 2 underway

East Bank August 2017

Ground Floor:   

Slab on ground complete

Western Power removed LV service

Transformer and LV frame installed – Waiting to confirm cable instillation date.

Mez Floor:        

Formwork stripping progressing

First Floor:        

Slab completed

Panels and columns completed

Second Floor:  

Pour 1 Ausdeck installed

Steel fixing commenced 

East Bank July 2017

Monthly update at Eastbank for July.

Ground Floor:   

Ground slabs completed up to area 4

Temp lighting and temp accommodation installed to ground floor carpark

Mez Floor:         

Slab completed

Precast walls and columns completed

Formwork to insitu sections underway – Pour booked for Thursday 3/8/17

First Floor:          

Pour 1 Ausdeck installed

Steel fixing progressing – Pour booked for Wednesday 2/8/17

August Targets,

Complete ground works and first floor, progress to the first floor structure

East Bank June 2017

Monthly update at Eastbank for June.

 

Ground Floor:

  • Tower crane installed
  • Ground works progressing – Residential footings to commence 3/7/17
  • Carpark slab and commercial tenancies poured
  • Pre-Cast - 3 x Core’s walls stood
  • Columns to commercial and carpark slabs
  • Perimeter walls stood to bottom of ramp
  • Mez Floor panels commenced

 

July Targets:

  • Complete ground works and Mez slab, progress to the first floor structure

East Bank May 2017

Works commenced 8/5/17.

Bulk earthworks completed, detailed excavations to footings underway.

Footings poured to crane, stair 2, SF1+2 and commercial 3.

Slab poured to commercial 3.

Piles to East and Southern elevations completed.

Deep sewer pipe work and mains connection completed

Tower crane install to go ahead 1/6/17

 

Works to progress out of the ground over the next month with column and panel instillations to commence as the slabs go down. 