Psaros / Projects / Under Construction

Projects under construction

Want to see how construction is progressing?

Please click on the project you would like to see a construction update for. Visit our Current Projects to see the superb opportunities still available at the sites under construction.

Sundance by Psaros

Sundance is now complete

Click to the website 

East Bank by Psaros

Current estimated completion date - Mid 2018

See the progress here.

Sundance is now complete

Click to the website 

Sundance Dec 17

Basement:

Line marking  70%

Ground Level:

Apartments pre snagging,  Footpath and crossovers 50%,  Screens and gates 40%.

Level 1

Apartments pre snagging, Lobby 80%

Level 2

Apartments pre snagging, Lobby 80%

Level 3

Apartments pre snagging, Lobby 80%

Level 4

Apartments pre snagging, Lobby 80%

Level 5

Timber flooring 50%, Tiling 100%, electrical and plumbing fit off 100%

Level 6

Tiling 100%, shower screens and mirrors in production, electrical and plumbing fit off 75%

Level 7

Cabinets 100%, stone tops 100%, Tiling over Christmas

External Works

Cladding 100%, screens 50%, painting 65%, Glass balustrade 95%

Pool Deck

Decking 90%, Tiling 60%, Gym & BBq area structure 100%, CFC sheeting 100%, Gyprock sheeting 100%, pool headers 60%

Sundance October 17

Basement is being cleaned ready for line marking.

Ground level apartments 100% waiting for courtyard screens

L1 Apartments 100%

Pool decking 30%

L2  Apartments 95%

L3 Apartments 95%

L4 Timber flooring 20%

L5 Tiling complete, prepping floors for timber.

L6 Cabinets 90%.

L7 Gyprock complete, flushing 40%

Sundance Sep 17

  • Basement  cleaning all storerooms.
  • Ground floor - all complete other than front balcony’s.
  • First floor – timber flooring 80%   carpets start Monday.
  • Second floor- levelling concrete floors ready for timber flooring.
  • Third floor –breezeway tiling complete internal tiling 70%.
  • Fourth floor- tiling breezeway today     internal tiling next week.
  • Fifth floor –kitchen install  60% waterproofing breezeway  Monday.
  • Sixth floor –fully framed 40% gyprocked scaffold strip Wednesday.  
  • Seventh floor –framing in progress –breezeway soffits in progress –roof cover complete Wednesday –screeding internally in progress.
  • Pool deck structural steel started, screeding planters started and torch on started.

Sundance August 2017

Basement

Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

Tiling complete

Final paint 95% complete

Level 01:

Unit 09 - 27

Stone tops 95% complete

Level 02:

Unit 28 - 46

Kitchens 10% complete

Level 03:

Unit 47 - 57

Sheeting flushing complete

 Level 04:

Unit 58 - 68

Sheeting 50% complete

Level 05:

Unit 69 - 79

Framing 50% complete

Level 06:

Unit 80 - 90

Services 50% complete

Level 07:

Unit 91 - 100

Structural steel 50% complete

Sundance May 2017

During the last 4 weeks we have completed the below

Basement:

  • Storerooms 45% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 06  

Level 01:

Unit 09 - 27

  • Level 01 formwork 100% stripped out
  • Level 01 Underslung plumbing 50% complete

Level 02:

Unit 28 - 46

  • Level 02 concrete poured 100% installed
  • Level 02 wall panels 80% installed

Level 03:

Unit 47 - 57

  • Level 03 Floor panels 50% installed

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor internal wall framing Unit 01 – 08  
  • Ground floor internal wiring and plumbing 100% complete

Level 01:

Unit 09 - 27

  • Ground floor internal wall framing

Level 02:

Unit 28 - 46

  • Level 02 formwork 100% stripped out
  • Level 02 underslung plumbing

Level 03:

Unit 47 - 57

  • Level 03 concrete poured 100% complete 

Sundance April 2017

During the last 4 weeks we have completed the below;

Basement:

  • 100% Formwork stripped out

Ground Floor:  

Unit 01 – 08

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured
  • 50% Formwork stripped out

Level 01:

Unit 09 - 27

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 50% installed
  • Level 01 50% Concrete poured

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 50% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 05  

Level 01:

Unit 09 - 27

  • Level 01 formwork 50% stripped out

Level 02:

Unit 28 - 46

  • Level 02 floor panels 100% installed
  • Level 02 wall panels 50% installed

Level 02 concrete poured 50% installed

Sundance March 2017

During the last 4 weeks we have been working on the below;

Basement

  • 100% Footings complete
  • Basement ground slab 100% complete
  • Basement precast walls and columns 100 % complete
  • 50% Basement formwork stripped out

Ground Floor

  • Ground floor precast floor panels 100% installed
  • Ground floor slab 75% Concrete poured

Level 01

  • Floor panels started

Over the next 4 weeks we will be working on completing the below;

Basement

  • 100% Formwork stripped out
  • Basement storerooms 20% Complete

Ground Floor

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured

Level 01

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 20% installed
  • Level 01 25% Concrete poured 

Sundance February 2017

During the last 4 weeks we will be have been working on the below:

Basement

  • 90% Footings complete
  • Basement ground slab 75% complete
  • Basement precast walls and columns 80 % complete

Ground Floor

  • Ground floor precast panels 50% complete

 

 

Sundance January 2017

During the last 4 weeks we will be have been working on the below:

Basement

  • 50% Footings complete
  • Crane base and Crane installation complete
  • Bulk excavation 90% complete
  • Precast concrete stairwell and lift shaft wall installation complete
  • Plumbing and electrical ground works 75% complete

Over the next 4 weeks we will be working on completing the below

Basement

100% Footings complete

  • Basement ground slab 75% complete
  • Basement precast walls and columns 50 % complete

Sundance December 2016

During December we have been working on:

Basement

  • Sheet piling 100% complete
  • Bulk Excavation 70% complete
  • Soakwell install 50% complete
  • Footing excavation 30% complete
  • Crane base and feet install 100% complete

:

Sundance November 2016

During the last 4 weeks we will be have been working on the below:

Basement

  • Sheet piling
  • Grout injection
  • Bulk excavation

Over the next 4 weeks we will be working on completing the below

Basement

  • 20% Footings
  • Crane base installation
  • Bulk excavation

Current estimated completion date - Mid 2018

See the progress here.

East Bank February 2018

GL Framing and tube out complete ready for sheeting 

L1 Fit off 80% Tiling complete Timber flooring starting 

L2 Fit off commenced Tiling 90%.

L3 Fit off commenced Tiling 75%.

L4 Tiling 5% Cabinets 80%.

L5 Sprayed out 50% Cabinets starting 

L6 Flushing 70% ready for paint 

L7 Studwork 100% gyprock starting 

East Bank December 2017

Ground Floor:    Window Frames Installed

                             Block work completed

                             Canopy steel completed

Mez Floor:          Underslung hydraulics and electrical progressing

First Floor:          Cabinets installed

                             First coat paint completed

                             Tiles commenced

Second Floor:    First coat paint commenced

                             Screed completed

                             Cabinets commenced

Third Floor:        Sheeting commenced

                             Screed completed

 Fourth Floor:    Pronto and frame work completed

                             Window frames installed

                             Screed completed  

Fifth Floor:         Pronto panel and blue board completed

                             Window frames installed                               

                             Screed completed

Sixth Floor:         Framing completed

Seventh Floor:   Pronto walls commenced

                             Canopy steel complete

                             Roof cover completed

East Bank Nov 17

Ground Floor:    Window Frames Installed

                             Block work completed

Mez Floor:          Underslung hydraulics and electrical progressing

First Floor:          Cabinets installed

                              First coat paint completed 

Second Floor:     First coat paint commenced

                              Screed completed

Third Floor:         Sheeting commenced

                              Screed completed

Fourth Floor:      Pronto and frame work completed

                              Window frames installed

                              Screed completed

Fifth Floor:          Pronto panel and blue board completed

                              Top and bottom track completed

 Sixth Floor:         Formwork stripped

                              Pronto set out

Seventh Floor:    Precast Walls completed

                              Roof cover commenced

                              Structural steel commenced

East Bank Sep 2017

Ground Floor:   Pronto walls commenced to ground floor units and tenancies.

                            Mech ducting instillations underway

                            Hydraulic instillations underway

                            Electrical instillations underway

 Mez Floor:        Brickwork to stores underway

                            Hydraulic and electrical instillations underway  

 First Floor:        Pronto panels 90% completed

                             Frame work underway

                             Hydraulic stack work underway

                             Electrical cabling underway

                             WPM to balconies underway

Second Floor:    Pronto panels commenced

 Third Floor:       Slab Completed, strip to commence week commencing 9/10/17

 Fourth Floor:     Ausdeck completed

                             Steel completed to pour 1 – Concrete 2/10/17

                             Steel to pour 2 underway

East Bank August 2017

Ground Floor:   

Slab on ground complete

Western Power removed LV service

Transformer and LV frame installed – Waiting to confirm cable instillation date.

Mez Floor:        

Formwork stripping progressing

First Floor:        

Slab completed

Panels and columns completed

Second Floor:  

Pour 1 Ausdeck installed

Steel fixing commenced 

East Bank July 2017

Monthly update at Eastbank for July.

Ground Floor:   

Ground slabs completed up to area 4

Temp lighting and temp accommodation installed to ground floor carpark

Mez Floor:         

Slab completed

Precast walls and columns completed

Formwork to insitu sections underway – Pour booked for Thursday 3/8/17

First Floor:          

Pour 1 Ausdeck installed

Steel fixing progressing – Pour booked for Wednesday 2/8/17

August Targets,

Complete ground works and first floor, progress to the first floor structure

East Bank June 2017

Monthly update at Eastbank for June.

 

Ground Floor:

  • Tower crane installed
  • Ground works progressing – Residential footings to commence 3/7/17
  • Carpark slab and commercial tenancies poured
  • Pre-Cast - 3 x Core’s walls stood
  • Columns to commercial and carpark slabs
  • Perimeter walls stood to bottom of ramp
  • Mez Floor panels commenced

 

July Targets:

  • Complete ground works and Mez slab, progress to the first floor structure

East Bank May 2017

Works commenced 8/5/17.

Bulk earthworks completed, detailed excavations to footings underway.

Footings poured to crane, stair 2, SF1+2 and commercial 3.

Slab poured to commercial 3.

Piles to East and Southern elevations completed.

Deep sewer pipe work and mains connection completed

Tower crane install to go ahead 1/6/17

 

Works to progress out of the ground over the next month with column and panel instillations to commence as the slabs go down. 