Basement: Shockcrete to perimeter walls completed, formwork to ramp walls and ramp commenced 

Ground Floor: Western power room doors installed, Fire rated duct work completed.

Level 1 (Units 1-10) Timber floors and tiling completed to units, lobby floor tiling underway

Level 2 (Units 11-20) Timber floors and tiling completed to units, lobby floor tiling underway 

Level 3 (Units 21-28) Tiling to units completed, external screed commenced following scaffold dismantle

Level 4 (Units 29-36) Balustrade complete, tiling complete to units, lobby floor tiling underway

Level 5 (Units 37-41) Kitchens cabinets complete, stone tops templates picked up.

General: External cladding complete and scaffold progressing down behind finishes. Display units progressing and finishes to all appartments progressing