The Chelsea March 2016

Basement: Ramp access cleared, excavation to commence Monday 4/4/16

Ground Floor: Temp amenities set up, formwork commenced stripping and back propping to first floor  

Level 1 (Units 1-10): Area 1 slab poured, AFS walls completed, formwork to level 2 slab commenced, Area 2 steel underway ready for slab pour Monday 4/4/16 

Level 2 (Units 11-20): Area 1 formwork 90% complete, steel work to commence Tuesday 5/4/16 

General: Site clean up underway and access points cleared. Small laydown established with permission from the neighbour for a 10m bin and some materials.