The Chelsea June 2016

Basement: Dewatering underway to area 1, CF1 poured, targeted excavations completed to area 1 pile caps, blinding poured to area 1, WPM commenced to area 1. 

Ground Floor: Hydraulic, mechanical and electrical services instillations continue. 

Level 1 (Units 1-10): Framework completed, Hydraulic, mechanical and electrical tube out 90% complete, screed to wet areas and balconies complete, windows and sliding doors complete, texture and skim coats 70%

Level 2 (Units 11-20): Framework completed, Hydraulic, mechanical and electrical tube out 90% complete, screed commenced to wet areas and balconies.

Level 3 (Units 21-28): Frame work commenced, Hydraulic, mechanical and electrical tube out 50% 

Level 4 (Units 29-36): Formwork stripped and clean up underway to units 21-24, hydraulic and electrical rough in commenced. 

Level 5 (Units 37-41): Level 5 slab complete, AFS walls commenced to units 37-39 and all panels delivered to site 30/6/16.

General: Framework to continue directly to next levels behind service instillations, basement works to proceed to CF2 and then hydraulic instillations.