The Chelsea July 2016

Basement: Dewatering underway to area 2, CF2 poured, area 1 slab complete, stair 1 and lift core walls poured. 

Ground Floor: Hydraulic, mechanical and electrical services instillations continue. 

Level 1 (Units 1-10): Gyprock completed, minor flushing to finish, crane void poured 

Level 2 (Units 11-20): Framework completed, Hydraulic, mechanical and electrical tube out complete, crane void poured   

Level 3 (Units 21-28): Frame work completed, Hydraulic, mechanical and electrical tube out 90%, crane void poured 

Level 4 (Units 29-36): Framework 85%, hydraulic and electrical rough in commenced 

Level 5 (Units 37-41): Level 5 roof 90%, steel canopies delivered & columns stood, Hydraulic, mechanical and electrical rough in 90%. 

General: Framework to continue directly to next levels behind service instillations, basement works to proceed to ramp area and then hydraulic instillations.