The start of the month began with the erection of the crane on site. Installation of AFS paneling are 50% to the ground floor and the completion of ground floor slabs.

The mezzanine floor was formed and concrete poured with columns formed to first floor level.

The perimeter AFS lintal beams are completed to Beaufort street followed by the installation of AFS on the Mezzanine level by 20%.

The remaining AFS on ground floor is currently being installed on Tiverton St.

Looking forward for March the first floor will be formed and poured.