The Chelsea August 2016

Basement: Dewatering continuing to ramp area, stair 1 walls poured, stair 2 and perimeter walls steel and formwork underway. 

Ground Floor: Hydraulic, mechanical and electrical services instillations continue. 

Level 1 (Units 1-10): Kitchen and bathroom fit off commenced 

Level 2 (Units 11-20): Kitchens cabinets complete, stone tops, electrical and hydraulic fit off to commence this week  

Level 3 (Units 21-28): Kitchens commenced, painting 80% 

Level 4 (Units 29-36): Wall Sheeting 90% 

Level 5 (Units 37-41): Frame work 90%, sheeting to commence Wednesday 

General: External cladding to level 3,4 and 5 progressing along with the external texture weather permitting.