The Chelsea April 2016

Basement: Excavation, 80% bulking removed, Dam under construction, Dewatering to commence 9/5/16 and targeted excavations to follow. 

Ground Floor: Hydraulic and electrical services instillations commenced. 

Level 1 (Units 1-10): Units 1 -6 formwork stripped and back propped, hydraulic stack work commenced, Unit 7 -10 waiting to be stripped once concrete is up to strength. 

Level 2 (Units 11-20): Slab completed, AFS walls 90% stood, Poured AFS to Area 1.

Level 3 (Units 21-28): Formwork to area 1 complete, Reinforcement to level 3 Area 1 to commence Monday 2/5/16. 

General: Removal of formwork and reduced propping to ground floor to open up some material storage area. Handrails to stairs completed up to formwork levels. Some minor disruption to works due to weather.