Sundance Sep 17

  • Basement  cleaning all storerooms.
  • Ground floor - all complete other than front balcony’s.
  • First floor – timber flooring 80%   carpets start Monday.
  • Second floor- levelling concrete floors ready for timber flooring.
  • Third floor –breezeway tiling complete internal tiling 70%.
  • Fourth floor- tiling breezeway today     internal tiling next week.
  • Fifth floor –kitchen install  60% waterproofing breezeway  Monday.
  • Sixth floor –fully framed 40% gyprocked scaffold strip Wednesday.  
  • Seventh floor –framing in progress –breezeway soffits in progress –roof cover complete Wednesday –screeding internally in progress.
  • Pool deck structural steel started, screeding planters started and torch on started.