Psaros / News

Sundance May 2017

During the last 4 weeks we have completed the below

Basement:

  • Storerooms 45% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 06  

Level 01:

Unit 09 - 27

  • Level 01 formwork 100% stripped out
  • Level 01 Underslung plumbing 50% complete

Level 02:

Unit 28 - 46

  • Level 02 concrete poured 100% installed
  • Level 02 wall panels 80% installed

Level 03:

Unit 47 - 57

  • Level 03 Floor panels 50% installed

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor internal wall framing Unit 01 – 08  
  • Ground floor internal wiring and plumbing 100% complete

Level 01:

Unit 09 - 27

  • Ground floor internal wall framing

Level 02:

Unit 28 - 46

  • Level 02 formwork 100% stripped out
  • Level 02 underslung plumbing

Level 03:

Unit 47 - 57

  • Level 03 concrete poured 100% complete