During the last 4 weeks we have been working on the below;

Basement

  • 100% Footings complete
  • Basement ground slab 100% complete
  • Basement precast walls and columns 100 % complete
  • 50% Basement formwork stripped out

Ground Floor

  • Ground floor precast floor panels 100% installed
  • Ground floor slab 75% Concrete poured

Level 01

  • Floor panels started

Over the next 4 weeks we will be working on completing the below;

Basement

  • 100% Formwork stripped out
  • Basement storerooms 20% Complete

Ground Floor

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured

Level 01

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 20% installed
  • Level 01 25% Concrete poured