During the last 4 weeks we will be have been working on the below:

Basement

  • 50% Footings complete
  • Crane base and Crane installation complete
  • Bulk excavation 90% complete
  • Precast concrete stairwell and lift shaft wall installation complete
  • Plumbing and electrical ground works 75% complete

Over the next 4 weeks we will be working on completing the below

Basement

100% Footings complete

  • Basement ground slab 75% complete
  • Basement precast walls and columns 50 % complete