Basement:

Line marking  70%

Ground Level:

Apartments pre snagging,  Footpath and crossovers 50%,  Screens and gates 40%.

Level 1

Apartments pre snagging, Lobby 80%

Level 2

Apartments pre snagging, Lobby 80%

Level 3

Apartments pre snagging, Lobby 80%

Level 4

Apartments pre snagging, Lobby 80%

Level 5

Timber flooring 50%, Tiling 100%, electrical and plumbing fit off 100%

Level 6

Tiling 100%, shower screens and mirrors in production, electrical and plumbing fit off 75%

Level 7

Cabinets 100%, stone tops 100%, Tiling over Christmas

External Works

Cladding 100%, screens 50%, painting 65%, Glass balustrade 95%

Pool Deck

Decking 90%, Tiling 60%, Gym & BBq area structure 100%, CFC sheeting 100%, Gyprock sheeting 100%, pool headers 60%