Sundance August 2017

Basement

Storerooms 100% complete

Ground Floor:  

Unit 01 – 08

Tiling complete

Final paint 95% complete

Level 01:

Unit 09 - 27

Stone tops 95% complete

Level 02:

Unit 28 - 46

Kitchens 10% complete

Level 03:

Unit 47 - 57

Sheeting flushing complete

 Level 04:

Unit 58 - 68

Sheeting 50% complete

Level 05:

Unit 69 - 79

Framing 50% complete

Level 06:

Unit 80 - 90

Services 50% complete

Level 07:

Unit 91 - 100

Structural steel 50% complete