Sundance April 2017

During the last 4 weeks we have completed the below;

Basement:

  • 100% Formwork stripped out

Ground Floor:  

Unit 01 – 08

  • Ground floor precast walls 100% installed
  • Ground floor 100% Concrete poured
  • 50% Formwork stripped out

Level 01:

Unit 09 - 27

  • Level 01 floor panels 100% installed
  • Level 01 wall panels 50% installed
  • Level 01 50% Concrete poured

Over the next 4 weeks we will be working on completing the below

Basement:

  • Storerooms 50% complete

Ground Floor:  

Unit 01 – 08

  • Ground floor underslung complete
  • Ground floor internal wall framing Unit 01 – 05  

Level 01:

Unit 09 - 27

  • Level 01 formwork 50% stripped out

Level 02:

Unit 28 - 46

  • Level 02 floor panels 100% installed
  • Level 02 wall panels 50% installed

Level 02 concrete poured 50% installed