Park Avenue - September 2016

During the last 4 weeks we will be have completed:

 

Basement

  • Area D – Basement footings 75% complete
  • Area B – Basement footings complete
  • Excavation for stairs & lift 04 complete
  • Storerooms in Area C complete
  • Basement to GF Ramp complete
  • Basement ramp from road complete
  • Concrete patching and grinding

Ground floor

  • Area A & C Internal framing complete
  • Area A & C External framing & Sheeting complete
  • Area A & C Electrical first fix, plumbing tube out & Mechanical complete
  • Area A & C Internal ceiling flushing complete
  • Structural silicone 50% complete internally

Level 01

  • Area A & C Internal framing 75% complete
  • Area A & C External framing & Sheeting 50% complete
  • Area A & C Electrical first fix, plumbing tube out & Mechanical 25% complete

Level 02

  • Area A Structural steel complete
  • Area C Formwork stripped out

Level 03

  • Area C Formwork stripped out

Level 04

  • Area C Precast walls 75% complete