Park Avenue May 2016

  • Over the last 4 weeks we have finalised 50% of the footings including crane base 01 and two lift/stairwell rafts.
  • The stormwater tank is 100% complete and waterproofed.
  • We are currently finalising the backfill around the tank.
  • The last week we have been preparing for the first ground slab concrete pour.