Park Avenue December 2016

In December the following activity was completed:

Area D

L4 slab pour

L4 walls 80%

L1 Framing 80%

GL Gyprock 40%

 

Area  B

Structural steel 80%

GL Gyprock 90%

L1 Framing 100%

GL tiling commenced

 

Area A

Tiling to L1 50%

Gyprock to L2 100%

Stone tops to L1

Doors and skirting to L2 100%

 

Area C

Gyprock 100%

Doors  and Skirting to L4 100%

Stone tops to L3