The crane base has been finalised and will be pouring the lift shaft and stairwell raft with footings along the west boundary today. We have also been dewatering and excavating the stormwater tanks which are 50m long.

Over the next 4 weeks they plan on working through the stormwater tank with the precast construction. They will also be aiming to finalise 30% of the footings.