Octo October 2014

The progress on site is coming to the closing stages of the project. We have completed all commercial apartments – and ready for inspections.

The residential apartments are approx. 2 to 3 weeks away from completion with only timber flooring, minor painting and services fit off to go. We have now booked in the purchaser inspection to start next week. Once we complete the commercial and residential apartments we will  start working on the common areas lifts front, entry, etc  from the top of the building down. We anticipate the complete the whole project (builders works) by the end of November 2014.