Octo August 2014

The roof is  now installed as such it has allowed us to commence the external texturing to the building, working from the top down. Weather pending we will complete the texturing within the next 3 to 4 weeks

Internally, we are working up the building. Level 1 & 2 commercial are almost complete, with some tiling, painting, cabinet install & carpeting to remain. We anticipate to complete commercial tenancies by end of October. Levels 3 & 4 apartments all walls and ceilings are almost complete. Cabinets to units 1 to 4 have commenced this week and will progress through to units 5 to 8. The next trades to follow will be the tiler, painter, carpenter.