  • Level one is in final snagging phase with purchaser inspections beginning next week
  • Levels 2 and 3 are almost complete and will enter snagging phase in next 2 weeks
  • Level 4 has walls & ceilings finished, kitchens and stone tops installed and tiling 50% complete
  • Level 5 walls and ceilings are complete and kitchens are now installed. Stone bench tops and tiling to progress over next month
  • The roof plant is almost finished, all solar panels are installed
  • The pool area is nearing completion
  • External facades are also nearing completion with scaffolding now mostly down.