Marq January 2015

  • Lifts are fully complete and operational
  • Pool is fully finished
  • Levels 1 & 2 have had their first inspections
  • Level 3 inspections are 5/6 February
  • Level 4 inspections are next week with the Level 5 inspections to follow shortly after
  • The public art has been installed and we are completing the entrance works at the moment
  • We have begun the process of gaining certification for the building