Ground Floor: Cabinets are in, stone measured installed next week, tiling commenced and floor prep for bamboo flooring later in the week

Level 1: Cabinets are in, stone measured and tiling commenced and floor prep for bamboo flooring later in the week

Level 2: Gyprock complete and painting next week

Level 3: Gyprock 90% complete, first fix carpentry starting on this Monday

Level 4: Start gyprock framing next week 

Common area: Walkways being prepared for texture 

Roof: 95% complete, will be 100% by middle of the week

External works: East and West elevations being prepared for texture next week

Fire services: 85%  complete