Hub April 2016

Ground Floor: Commenced wet areas screeding and gyprock – cabinets measured, glazing complete.

Level 1: Screeding next week along with gyprock, glazing completed.

Level 2: Framing/tube outs/cabling to apartments, glazing completed. 

Level 3: Stripping formwork ready for underslung pipe work next week, glazing booked for late next week. 

Level 4: Poured concrete columns – Structural Steel next week for roof framing, stand AFS walls to apartments, roof trusses booked for mid May.

Common Areas: Fire service being installed, common area retic being installed, electrical mains cabling to apartments being installed.