Flo October 2014

In the last month we have poured the complete 5th floor suspended slab and also poured the slab and walls to the pool area. We have started stud framing to levels 1 and 2 internally. Internal and external rendering has also commenced. We have also started standing ritek walls on level 5.

In the next month we will be contuining stud framing on levels 2, 3 & 4 along with all other internal fit out etc. Roof structure will commence in mid November. We will also be standing the walls to the gym and BBQ pavilion. We would also hope to have the roof structure well underway on both these by the end of November.