Flo November 2014

Level 1Internal fit out has started. All cabinetry will be complete by Christmas. Tiling has started and will be complete early January

Level 2Gyproc Sheeting will commence on Monday 1/12/14.

Level 3Internal Stud Framing is in progress. Complete by Wednesday 3rd December

Level 4Stud framing starting 4th December

Level 5Roof Cover has started on Area 1 and will be complete by 8th December. Roof Trusses to Area 2 started 27/11/14 and roof cover will be complete to this area by 19/12/14.

GymRoof Cover to be complete by Monday 1/12/14. Internal fit out to start next week.

BasementSprinkler system to be installed in December. Brickwork to also start on store rooms.

BBQ PavilionRoof Cover by Christmas.