Flo March 2015

INTERNAL

Level 1 (Units 1-14): Practically Complete internally. Awaiting external finishes

Level 2 (Units 15-32): Practically Complete.

Level 3 (Units 33-50): Painting and electrical fit off in Progress. Practical Completion in late April.

Level 4 (Units 51-68): Tiling and internal carpentry in Progress

Level 5: (Units 69-86): Fitting Kitchen cabinets and painting in progress

Basement: Fitting doors to all stores.

 

EXTERNAL

BBQ Pavilion: Ready for decking and stone bench top.

Pool Area: Ready for decking and pool lining.

Gym: Complete internally. Ready for decking externally

Block work has started to all planter beds and walkways.