Flo June 2015

Basement: Final snagging in progress. Line marking complete. Painting in progress.

Level 1 (Units1-14): Ready for purchaser inspections.

Level 2,3 & 4 (Units 15-68): Working on purchasers rectification lists.

Level 5 (Units 69-86): Purchaser inspections in progress

External: Cladding, artwork, signage and landscaping in progress.

This project will be complete in July.