Edge September 2015

Level 8: Slab complete and installation of panels commenced

Level 7: Strip out commenced and windows complete

Level 6: Framing 70%

Level 5: Framing 100%, plasterboard 40%

Level 4: Plasterboard 100%, Cabinets 100%, Tiling screed 100%, Paint 1st coat

Level 3: Plasterboard 100%, Cabinets 100%, Tiling 70%, Paint 1st coat

Level 2: Plasterboard 100%, Cabinets 100%, Tiling 100%, Paint 75%, Shower screens 80%, Robes 100%, Mirrors 80%, Appliances fitted.

Carparks: Services 95%