Psaros / News

Edge October 2015

Ground floor shop fronts measured, fire doors fitted, services 98%. Electrical Switchboards being fitted off, pump roof fitted off.

Level 1: Carpark, car stackers to upper level 40%

Level 2: Completed except carpet and timber floor

Level 3: Completed except carpet and timber floor

Level 4: Tiling being completed, fitoff fittings and fixtures 85%, internal doors fitted

Level 5: Kitchens 90%, Tiling commencing 4/11/15, paint 50%, internal doors fitted

Level 6: Gyprock 95%, Painting commencing 5/11/15

Level 7: Framing 100%, services rough in 90%, Gyprock commencing 5/11/15

Level 8: Stripped 55%, Sewer stacks 40%, Framing commencing 5/11/15

Level 9: Slabs complete, concrete walls 40%, walls to complete 13/11/15

Level 10: Slab form 30%, reinforcement to commence 6/11/15