The mezzanine level slab has been formed and poured at the rear of the site. All columns for the ground floor are in position. 60 % of the ground floor slab has been poured. The firewater holding tanks are currently being constructed.
Formwork for the level 1 car park is currently being placed. All structural works to the ground floor will be completed by the Xmas break, along with 90% of the 1st floor formwork, Works are on program.