Psaros / News

Edge November 2015

Ground floor shop fronts measured and fire doors fitted.

Level 1: Carpark, car stackers 90%

Level 2: Completed except carpet

Level 3: Complete, timber floors installed, carpets in Jan/Feb '16

Level 4: Complete, floor finishes commenced, final paint to follow

Level 5: Complete except floor finishes and final paint

Level 6: Kitchens, tiling complete, painting 80%, fit off in progress, internal doors fitted

Level 7: Gyprock, kitchens complete, painting, tiling and fitout in progress

Level 8: Wall framing, gyprock complete, kitchen installation commenced

Level 9: Slab complete and stripped, stud wall installation and plumbing commenced

Level 10: Slab complete, Concrete walls 85%

Level 11: Form 70%, reinforcement in progress, slab to be poured 11/12/15

Solar panels delivered and East boundary walls being textured/coloured.