Works at Edge are continuing to progress well, the 3rd floor slab was poured this month and works to the construct the structural  walls to the apartments are well underway. The formwork has commenced to enable the 4th floor slab to be poured mid-June.

The Fire pumps were delivered this month and work to install them is underway as is the sprinkler system and hydrants to the car park areas.

The electrician has commenced installation of cabling and lights to the car park areas, with 50% of the lighting in these areas now functional.

The car stackers are being delivered next month from Germany and works will commence to install these as they arrive.