Edge March 2016

Level 2 – Level 8 is now complete

Level 9: Fitted off, flooring commenced

Level 10: Kitchens are complete, tiling 95%, Paint 70%

Level 11: Walls/ceilings complete

The roof is complete and the carpark is being cleaned and detailed.

Solar Panels are 60% fitted

External walls are 75% painted

Scaffold is being removed and the Pool is tiled