Level 1: (Carpark): Brickwork to stores in progress

Level 2: (Units 1-8): Gyprock lining in progress.

Level 3: (Units 9-22): 1st fix plumbing, electrical and acoustic lagging in progress. Stud framing in progress.

Level 4: (Units 23-36): Standing Ritek walls

Level 5: (Units 37-50): Formwork, Reinforcement placement in Progress.

The aim for July is to pour Level 5's  slab and continue with ritek walls on Level 5. Internal fit out will continue on Levels 2 and 3.