Edge July 2015

Level 2: Stores, Kitchen and Bathroom cabinet installs complete.

Level 3: Gyprock linings to all walls, stop and set ready for paint on Monday 3 Aug

Level 4: Framing 60%, Services 70% and gyprock lining commencing Monday 3 Aug

Level 5: Ritek walls 90%

Level 6: Formwork at 60%, slab scheduled for 11 Aug