Edge February 2015

Works have now been completed to the ground floor slab with all of the inground services being installed. The ground floor walls are 95% complete and the 1st Floor formwork is well underway with the slab being poured by Mid-march. Works are also commencing to the Level 2 Formwork on the upper 1st level.

All works are on program