Ground Floor:   Pronto walls commenced to ground floor units and tenancies.

                            Mech ducting instillations underway

                            Hydraulic instillations underway

                            Electrical instillations underway

 Mez Floor:        Brickwork to stores underway

                            Hydraulic and electrical instillations underway  

 First Floor:        Pronto panels 90% completed

                             Frame work underway

                             Hydraulic stack work underway

                             Electrical cabling underway

                             WPM to balconies underway

Second Floor:    Pronto panels commenced

 Third Floor:       Slab Completed, strip to commence week commencing 9/10/17

 Fourth Floor:     Ausdeck completed

                             Steel completed to pour 1 – Concrete 2/10/17

                             Steel to pour 2 underway