East Bank Nov 17

Ground Floor:    Window Frames Installed

                             Block work completed

Mez Floor:          Underslung hydraulics and electrical progressing

First Floor:          Cabinets installed

                              First coat paint completed 

Second Floor:     First coat paint commenced

                              Screed completed

Third Floor:         Sheeting commenced

                              Screed completed

Fourth Floor:      Pronto and frame work completed

                              Window frames installed

                              Screed completed

Fifth Floor:          Pronto panel and blue board completed

                              Top and bottom track completed

 Sixth Floor:         Formwork stripped

                              Pronto set out

Seventh Floor:    Precast Walls completed

                              Roof cover commenced

                              Structural steel commenced