East Bank May 2017

Works commenced onsite 8/5/17.

Bulk earthworks completed, detailed excavations to footings underway.

Footings poured to crane, stair 2, SF1+2 and commercial 3.

Slab poured to commercial 3.

Piles to East and Southern elevations completed.

Deep sewer pipe work and mains connection completed

Tower crane installed.

 

Works to progress out of the ground over the next month with column and panel instillations to commence as the slabs go down.