Works commenced 8/5/17.

Bulk earthworks completed, detailed excavations to footings underway.

Footings poured to crane, stair 2, SF1+2 and commercial 3.

Slab poured to commercial 3.

Piles to East and Southern elevations completed.

Deep sewer pipe work and mains connection completed

Tower crane install to go ahead 1/6/17

 

Works to progress out of the ground over the next month with column and panel instillations to commence as the slabs go down.