East Bank June 2017
Monthly update at Eastbank for June.
Ground Floor:
- Tower crane installed
- Ground works progressing – Residential footings to commence 3/7/17
- Carpark slab and commercial tenancies poured
- Pre-Cast - 3 x Core’s walls stood
- Columns to commercial and carpark slabs
- Perimeter walls stood to bottom of ramp
- Mez Floor panels commenced
July Targets:
- Complete ground works and Mez slab, progress to the first floor structure