East Bank July 2017

Monthly update at Eastbank for July.

Ground Floor:   

Ground slabs completed up to area 4

Temp lighting and temp accommodation installed to ground floor carpark

Mez Floor:         

Slab completed

Precast walls and columns completed

Formwork to insitu sections underway – Pour booked for Thursday 3/8/17

First Floor:          

Pour 1 Ausdeck installed

Steel fixing progressing – Pour booked for Wednesday 2/8/17

August Targets,

Complete ground works and first floor, progress to the first floor structure