East Bank February 2018

GL Framing and tube out complete ready for sheeting 

L1 Fit off 80% Tiling complete Timber flooring starting 

L2 Fit off commenced Tiling 90%.

L3 Fit off commenced Tiling 75%.

L4 Tiling 5% Cabinets 80%.

L5 Sprayed out 50% Cabinets starting 

L6 Flushing 70% ready for paint 

L7 Studwork 100% gyprock starting