Psaros / News

East Bank August 2017

Ground Floor:   

Slab on ground complete

Western Power removed LV service

Transformer and LV frame installed – Waiting to confirm cable instillation date.

Mez Floor:        

Formwork stripping progressing

First Floor:        

Slab completed

Panels and columns completed

Second Floor:  

Pour 1 Ausdeck installed

Steel fixing commenced