Depot September 2015

Ground Floor – works commencing on lobby fit out , preparing for flooring to units on ground floor.

First Floor – preparing for flooring to units, completing works to car park ready for line marking and signage.

Second Floor – Final stages of fitting out apartments and preparing for flooring, balconies to be tiled by mid month, common area ceilings are painted and ready for electrical fit off, aiming to have common area walkways tiled by the end of the month.

Third Floor – Final stages of fitting out apartments and preparing for flooring balconies to be tiled by mid month, common area ceiling commencing later this week. Aiming to have walkways tiled by end of the month.

Loft Level – Currently gyprocking and kitchens have been made ready to install once painted. External cladding & roof sheeting complete, and external cladding 95% completed. Window frame install commencing and aiming to have all cabinets in by the end of the month and have tiling commencing.

External works – Exotec Cladding on South Elevation completed where possible – waiting on scaffold dropping. Exotec Cladding commencing on East elevation commencing later this week. Starting to complete works on Ground Floor car park area.