Depot October 2015

Ground Floor – Apartment Floors prepped, sanitary fixtures installed
First Floor - Apartment Floors prepped, sanitary fixtures installed
Second Floor – Internal glazing and robes, sanitary fixtures installed, tiling and screed to balconies.
Third Floor – Stone tops have been installed, Internal glazing and robes completed, balcony tiles and screeding completed, fourth floor cabinetry loaded out and stored.
Fourth Floor –  Services prelay completed, with wall linings flushed , External wall planters completed.
Loft – Windows have been completed, external cladding 90%, East Elevation balcony roof completed, LVL’s have been cladded.  Scaffolding L5 Removed
Roof -  Solar Hot water panels installed
Crane Removed