Psaros / News

Depot October 2014

We have completed all concrete works with regards to the car stacker pit.

We hit a mile stone today by installing the crane. This will now allow us to commence on other stages of works:

  • Pour footings
  • Pour ground slab
  • Install soak wells
  • Commence standing up walls to the ground floor

The above works will bring us up to Christmas.